 |
Inclusion Zone Redevelopment, Donegall Pass, Belfast: Concept & Envisioning Feasibility Study, January 2009 .
- EXECUTIVE SUMMARY
- CONTEXT & BACKGROUND
- THE EXISTING BUILDING
- INITIAL OPTIONS SIFT
- DESIGN PROPOSALS
- DESIGN DRAWINGS
- CONSTRUCTION COSTS
- ECONOMIC/FINANCIAL CONSIDERATIONS
- CONCLUSION
Appendix A: Condition Survey, Existing Building (Inclusion Zone) Appendix B: Schedule of Existing Accommodation – Donegall Pass Community Forum Offices, Grove House Appendix C: Crèche and Nursery Options Appendix D: Discussion Document for Sustainable Measures Appendix E: Best Practice Examples Appendix F: Practice Information – Consarc Design Group and EPEC
1. EXECUTIVE SUMMARY
Following a submission to Donegall Pass Community Forum in March 2008, Consarc Design Group and epec were commissioned to undertake a Concept & Envisioning Feasibility Study for the redevelopment of the ”Inclusion Zone” site which is located at the junction of Donegall Pass and Conduit Street.
The concept study has been funded by Belfast City Council through its ‘Neighbourhood Economic Development Programme’, and the intention of the study is to position the project for further development and funding.
The report will address the context and background of the project. Much work has already been carried out by the Donegall Pass Forum, and other initiatives in the community are already underway or recently completed, notably the study and report Donegall Pass: Towards a Sustainable Community (June 2008).
The above study was funded by the Belfast Local Strategy Partnership through the special support programme for Peace and Reconciliation, in partnership with Queens University Belfast. This is a valuable and complementary support document to this concept study.
The report addresses a range of options for the site, and sifts these options, culminating in a preferred model which best addresses the client’s aspirations and objectives.
The importance of creating, embracing the low carbon design initiative has been addressed, and a discussion document for sustainable measures included as an appendix to the report. It its intended that this document is reviewed as the project progresses.
We were conscious that any future project is likely to depend on funding from central government and other bodies, and therefore our approach was to offer a proposed building model which is flexible and can cope with future community needs and market demands. Best practice models have been studied and some are included in this project.
The design proposals are described and illustrated. A preliminary cost plan and estimate is included.
2. CONTEXT & BACKGROUND
The existing Inclusion Zone building is located at the junction of Donegall Pass and Conduit Street, in the Shaftesbury Ward in Belfast. The Shaftesbury Ward is recognised as an area of Social Need. However as the area lies between the city centre and South Belfast there is a, largely unrealised, commercial potential, evidenced by office buildings and restaurants. The area is also a focus for the Chinese community in Belfast.
Constructed in c. 1910, the building has had a number of uses, from school, to church, to youth club, but has deteriorated significantly in recent years and is something of an eyesore in its present state. Appendix A to this report is a record of the condition of the building on 1st May 2008.
The Donegall Pass Community Forum is presently located on the 3rd floor of Grove House, Donegall Pass. Formed in 1996, the Forum’s purpose is to facilitate and represent groups and agencies to further the regeneration of the Donegall Pass area and enhance the quality of life of all the people of the area. Four full-time and one part-time staff are employed in the Forum.
Belfast City Council, through its various initiatives, including the Neighbourhood Economic Development Programme, is keen to support development proposals which define, consolidate and enhance the neighbourhoods which make up the city.
Belfast City Council is therefore acting as a catalyst for community focused and sustainable development that can regenerate key issues.
3. THE EXISTING BUILDING
The existing building, located at the junction of Donegall Pass and Conduit Street, has had numerous uses through its life. In recent years the building has deteriorated dramatically and has fallen into a state of disrepair. Large holes in the slate roof cover are evident and this has allowed rainwater ingress, in particular to the main hall located at first floor level.
The costs to refurbish and restore this existing building would be significant. Our Quantity Surveyors estimate that the 535m² floor space could be in the region of £650,000 construction costs.
The existing architectural form does in some manner contribute to the character of the Pass, offering a tower feature to the street corner and an ecclesiastic window pattern to the first floor. The ground floor treatment to the main elevation is not so good, with a clumsy ‘shopfront’ projection which may have been an addition to the original frontage. The side and rear elevations to the building are poor, expressionless, dull and arguably ugly.
Internally, the building layout has been adapted through its life to suit the various uses. Circulation is presently unclear and convoluted, and level differences through the building add further to the clarity and ease of circulation. The interior is dark and unwelcoming, and access for wheelchair users is restricted. There is no access at all to the first floor for wheelchair users.
It is possible that the existing building could be restored and reused with some difficulty, although the opportunity to introduce new and vibrant components to the building will not be as successful as a new build solution. The opportunity to introduce a memorable, iconic landmark building to revitalise the Donegall Pass area and announce that the community looks to the future may be lost if the refurbishment option is favoured.
As an architectural practice with a track record of conserving the best of the historic built environment, the refurbishment option is always an important starting point, but should only be effected if it is capable of fulfilling the client’s demands and objectives.
In this case the demands of accessibility, sustainability, costs in use etc., lead us to consider carefully and investigate fully a new build solution.
A condition survey of the property is included in Appendix A of this report.
4. INITIAL OPTIONS SIFT
Introduction/Methodology
An initial wide-ranging exercise was undertaken, drawing on desk research, consultation and analysis of the surrounding area. The object of this exercise was to establish all possible realistic uses for the building, or site where the subject building is replaced.
These potential uses are set out in the following table along with an analysis of the relevance and fit to the Donegall Pass. Those which pass this initial filter, indicated in bold in the table, are carried through to the ‘short list’ that follows. That short list then considers the requirements of each possible use, with a view to determining which can be accommodated, which can co-exist, or not, and which have particular requirements, such as a ground floor position.
Long List:
|
Use
|
Analysis/comment
|
|
Mini-market
|
Reasonable existing provision especially since recent opening on Dublin Road, hence while possible, this could not be a priority, would also be unlikely to justify public funding given the lack of additionality.
|
|
Community gym/sports hall
|
Existing provision at Shaftesbury Recreation Centre, currently under expansion. A full-size sports hall would not fit on the site. There remains the potential for more limited needs.
|
|
Café/coffee shop
|
Under-represented, despite the presence of a number of restaurants (in part a reflection of the presence of a Chinese community in the area). This form of provision would be valuable in bringing vibrancy of Botanic area into Pass.
|
|
Arts centre/Gallery
|
Sustainability concerns – though an arts relevance would be desirable.
|
|
Health related – including Healthy Living Centre
|
The site is small for a ‘full service’ Healthy Living Centre, such as that at Albert Street in the west of the city. However the HLC model spans a number of forms, including co-existing with community development, eg EBCDA in East Belfast. The key documents describing HLCs are: 1. Department of Health. Our healthier nation. London: DH, 1998. 2. Institute of Public Health in Ireland. Evaluation of healthy living centres in Northern Ireland: a summary. Belfast: IPH, 2007. 3. Bridge Consortium. The evaluation of the big lottery fund healthy living centres programme: final report. London: Tavistock Institute, 2006. 4. Department of Health, Social Services and Public Safety. A healthier future: a twenty year vision for health and wellbeing in Northern Ireland 2005-2025. Belfast: DHSSPS, 2004. 5. Department of Health, Social Services and Public Safety. Investing for health. Belfast: DHSSPS, 2002. 6. Department for Social Development. People and place: a strategy for neighbourhood renewal. Belfast: DSD, 2003. 7. Northern Ireland Executive. Review of public administration. www.rpani.gov.uk Last accessed 8 September 2008.
A briefing paper Healthy Living Centres – A model for the delivery of neighbourhood health (HPA, September 2008) was developed by the Healthy Living Centre (HLC) Regional Alliance and the HPA. It provides information on how HLCs, as part of the local health economy, deliver their work in implementing health policy, and what services they deliver. The funding model is though in state of change, 2 of the original 19 HLCs in Northern Ireland having closed. Given this current uncertainty this option was not developed further. However the exploration of the potential to attract an HLC to the Pass area should be examined when clarity on funding has improved.
|
|
GP Practice/possibly co-located Dentist
|
No expressed need has been raised, such demand as exists could usefully regenerate other buildings in the area.
|
|
Education/Training
|
These are highly valuable uses, ones that change through the day, but at all times requiring appropriately sized and equipped rooms
|
|
Crèche (including nursery and related childcare activities)
|
There is a strong demand for child-care, both within the locality and in relation to those who work in city centre Belfast. This form of provision has a proven income model, indeed it is commonly provided on a fully commercial basis. The opportunity for a social economy operation is however present here, where the activity can be used to provide training and other benefits into the Donegall Pass area. Childcare is important in that it aids wider objectives around supporting women in work, consequently it would be a highly useful ‘first building block’ in the renewal of the area.
|
|
Incubation units
|
This form of workspace facilitates enterprise and business rooted in locality, certain sectors such as craft and antique repair/bookbinding etc sitting very well with area’s traditional retail mix.
|
|
Youth (to mean youth specific provision – note that under any of the development options young people would be encouraged to access the resource along with all others)
|
Limited existing youth provision is available elsewhere in the locality, since the closure of the building that is the subject of this report. That closure was allowed, without precipitating replacement, suggests that the case for substantial youth provision was not made at the time. Youth provision would require a hall and ancillary rooms that would fill the entire site considered here. Consequently it could not be delivered within a shared building. There remains however a need for dedicated youth provision, which is adequately funded to provide necessary levels of staffing. This should be pursued with the relevant statutory agency.
|
|
Affordable and Social Housing
|
There is traditionally a strong demand for affordable housing, at the time of writing, late 2008, current difficulties in the housing market have reduced this demand. Affordable housing contributes to maintaining community and confers other important social benefits and is thus potentially valuable. However traditionally the ground floor corner sites on the front of a major road (with terraces off) would have a non-residential nature, reflecting their importance, for example a shop. This suggests directing any affordable housing use to either upper floors or the Posnett Street frontage, or both. Another attraction of affordable housing for sale is that it is largely self funding, generating a considerable contribution from the purchaser. Further, there are no ongoing costs.
|
|
Social economy
|
The ‘not for profit sector’ or social economy is an important occupier of space in the edge inner city. The site could provide office, and possibly also trading space, for various charities and other bodies. The acceptability of area is demonstrated by the recent construction of the NIACAB (Citizen’s Advice) building across the road from the subject site, plus a number of others.
|
|
Community hub
|
There is growing interest in partnership within and between community organisations and voluntary bodies, as these raise efficiency and lower costs. A prime example, developed for example in Rathcoole (Dunanney Centre) is a community hub that provides a range of spaces for organisations that facilitate residents in accessing services (eg ‘one stop shop’) and also benefit the organisations themselves through the promotion of networking
|
|
Short List:
The uses that qualify for further consideration are set out below, along with their space implications:
|
Use
|
Analysis/comment
|
|
Housing
|
Unit size from 50sqm (one bed studio) to 65 sqm (two bed)
|
|
Café
|
Ground floor, frontage to Pass, possibly to corner, café space of xx covers, plus prep kitchen and storage
|
|
Gallery uses
|
Room of 30 sq m or larger (can include circulation space, eg. Corridor)
|
|
Crèche
|
Guidelines require space to include quiet room and optionally outside space for a crèche for children
|
|
Education/training
|
’classroom’ style provision is 10-40 sq m per room, smaller rooms used for more focused training – also supporting rooms for one to one and tutorials, etc.
|
|
Community hub
|
Meeting rooms – large 60 sq m and small 30 sq m. Also administration offices – for 6 workers totalling approx 80 sq m
|
|
Incubation units
|
Own front door and ground floor, hence Conduit Street frontage is sole suitable location
|
|
Social economy
|
Space dependent on use and scale, eg 8 sq m per employee if offices plus minimum 20 sq m (ground floor) for any trading function
|
|
Minimum circulation
|
Allow 15% of total internal area
|
|
Toilets and service
|
Allow 50-80 sq m
|
|
Analysis:
A series of workshops were held with the client, and consideration given to the introduction of all of the above short list to the building design. An emphasis was placed on achieving a balance of uses within the building. The two reasons for this were, firstly, the need to ensure that all sections of the community would see benefit and, secondly, that by spreading the use of the building over multiple activities, it would be easier to ensure long term sustainability. Consequently, flexibility was a key requirement of the building design.
5. DESIGN PROPOSALS
Following a detailed discussion with the Board of Trustees of the Donegall Pass Community Development Company Ltd, consideration of the options available, including refurbishment of the existing building, a clear mix of uses emerged which defines the proposal as a community based, iconic statement.
The new building should be welcoming, for young and old, modern, and the hub of the Donegall Pass community. The accommodation is arranged on ground and three upper floors, similar in scale to the newly constructed Citizens Advice Bureau opposite, and making best use of the available footprint of the development site.
The key components of the proposed building are as follows:-
- A café, located prominently on the Donegall Pass frontage and which has an outside terrace which utilises the wide footpath on Donegall Pass.
- A reception area where the visitor is directed to other parts of the building, a meet and greet and information point.
- Male, Female and Disabled public toilets located at various levels.
- Suite 1, located behind the reception, is a 74m² flexible space which could be let as an incubator / start-up unit, or indeed could accommodate the Donegall Pass Community Forum offices.
- The first floor accommodation comprises a large (68m²) flexible community space, which can accommodate up to 60 people for community meetings, presentations, or functions. The room is flexible, allowing it to be rearranged in a variety of ways. Large screen doors open to allow the room to extend to a gallery space which overlooks the cafe below. This is potentially a vibrant, memorable architectural space which defines the building and gives it civic scale and quality.
- A meeting room (27m²) is prominently located at first floor level on the corner of Donegall Pass and Conduit Street, shaped to provide the distinctive architectural building form which addresses the corner of the building and the main entrance under.
- A 42m² Information Technology Room is located to the rear of the building. This important facility can also be used as a meeting room if required.
- The second floor accommodation is arranged to provide flexible spaces which can be used as meeting rooms, incubator/start-up units, or dedicated short term tenancies. The architectural layouts indicate that the Forum offices can be accommodated here, overlooking Donegall Pass.
- The third floor is dedicated to a professionally managed and operated crèche facility, comprising 3 play zones, a small kitchen, a central meeting room and tea point, and two outdoor play areas. The building frontages to the front and rear are set back to allow paved and landscaped terraces to be introduced. Play Zone 1 can accommodate 8 children from 0-2 years; Play Zone 2 can accommodate 8 children from 2-3 years; and Play Zone 3 can accommodate 8 children from 3-5 years.
Conscious of the safety and protection of children in a mixed-use, accessible building, the upper floor location of the crèche provides the necessary security for its users and allows the necessary provision of fully protected outdoor play areas. The design of this mixed use community building has been challenging and the template produced has taken account of the key elements which made it through the sift of many other suggested components.
Its flexibility means that as and when priorities change the building can adapt to take account of other uses, for example, a small gymnasium, or dedicated studio space.
The building can be an exemplar model for this important urban project, which should be firmly rooted in the Donegall Pass community. It should be open to all, and in return the Donegall Pass community should feel ownership of this building, look after and maintain it, and most importantly, use it regularly to benefit all sections of the community.
6. DESIGN DRAWINGS
Download/view associated pdf file for the above (File size: 3.25Mb.)
Download/view associated pdf file for the above (File size: 1.93Mb.)
Download/view associated pdf file for the above (File size: 4.08Mb.)
7. CONSTRUCTION COSTS
|
Executive Summary
|
|
|
|
|
|
|
|
Preliminary Estimated Cost
|
Total
|
Cost/M2
|
|
|
Community Forum
|
1,255 M2
|
1,433,076.50
|
1,141.89
|
|
|
|
|
|
|
|
|
Preliminaries 15%
|
|
214,961.68
|
|
|
|
|
|
|
|
|
|
Contingency Sum 5%
|
|
82,401.90
|
|
|
|
|
|
|
|
|
|
Low Carbon Measures (Provisional Sum) 10%
|
173,043.99
|
|
|
|
|
|
|
|
|
|
|
|
£ 1,903,483.86
|
|
*
|
|
|
|
|
|
|
|
|
|
Gross Floor Area
|
1,255
|
M2
|
|
|
|
|
13,509
|
Sq Ft
|
|
|
|
Cost/M2
|
£ 1,517
|
|
|
|
|
Cost/Sq Ft
|
£141
|
|
|
|
|
|
|
|
|
* Excludes
|
VAT
|
|
|
|
|
|
Professional Fees
|
|
|
|
|
|
Building Control and Planning Fees
|
|
|
|
|
Site Acquisition Costs
|
|
|
|
|
|
Development Funding
|
|
|
|
|
|
Legal Fees
|
|
|
|
|
|
Removal of contamination
|
|
|
|
|
Fit-out – cafe, forum, crèche
|
|
|
|
|
Archaeology
|
|
|
|
|
|
Kitchen
|
|
|
|
|
|
Elemental Summary
|
|
|
|
|
|
|
|
|
|
%
|
£/M2
|
£
|
|
Demolitions and Alterations
|
3
|
39.84
|
50,000.00
|
|
|
|
|
|
|
|
Substructure
|
|
4.68
|
53.39
|
67,000.00
|
|
|
|
|
|
|
|
Frame
|
|
9.20
|
105.02
|
131,800.00
|
|
|
|
|
|
|
|
Upper Floors
|
|
3.33
|
38.05
|
47,750.00
|
|
|
|
|
|
|
|
Roof
|
|
5.73
|
65.48
|
82,175.00
|
|
|
|
|
|
|
|
Stairs
|
|
2.09
|
23.90
|
30,000.00
|
|
|
|
|
|
|
|
External Walls
|
|
7.21
|
82.37
|
103,380.00
|
|
|
|
|
|
|
|
Windows and External Doors
|
3.69
|
42.12
|
52,860.00
|
|
|
|
|
|
|
|
Internal Walls
|
|
3.78
|
43.19
|
54,204.00
|
|
|
|
|
|
|
|
Internal Doors
|
|
2.84
|
335.58
|
42,140.00
|
|
|
|
|
|
|
|
Wall Finishes
|
|
3.76
|
42.97
|
53,932.00
|
|
|
|
|
|
|
|
Floor Finishes
|
|
5.57
|
63.62
|
79,838.00
|
|
|
|
|
|
|
|
Ceiling Finishes
|
|
2.71
|
30.90
|
38,785.00
|
|
|
|
|
|
|
|
General Fittings
|
|
3.17
|
36.25
|
45,500.00
|
|
|
|
|
|
|
|
Mechanical & Electrical Installation
|
32.18
|
367.50
|
461,212.50
|
|
|
|
|
|
|
|
Lift Installation
|
|
2.97
|
33.86
|
42,500.00
|
|
|
|
|
|
|
|
Siteworks/Connection charges
|
|
|
50,000.00
|
|
|
|
|
|
|
|
TOTAL BUILDING WORK
|
96.51
|
1,141.89
|
1,433,076.50
|
|
|
|
|
|
|
|
Gross internal floor area (M2)
|
|
1,255.00
|
M2
|
|
Gross internal floor area (Sq. Ft.)
|
|
13,508.82
|
Sq. Ft.
|
|
|
|
|
|
|
|
COST PER M2
|
|
|
£1,141,.89
|
/M2
|
|
COST PER Sq. Ft.
|
|
|
£106.08
|
/Sq. Ft.
|
|
8. ECONOMIC/FINANCIAL CONSIDERATIONS
This section presents an overview of the business model for the building. It presents an indicative income stream and the associated cost structure before combining these to render a conclusion of sustainability.
Operating Cashflow statement: Costs
The table below sets out the projected annual costs of operating the proposed building. This cashflow assumes that there is no loan interest or repayment on the capital cost of the building.
|
COSTS (annual)
|
|
|
Staffing – a dedicated networking officer, responsible for management of buildings, lettings, financial arrangements etc., promotion and hosting of events and networking activities, plus out of hours opening/caretaking
|
£30,000
|
|
Heat, light and power (under a low carbon specification)
|
£8,000
|
|
Cleaning
|
£2,500
|
|
Insurances and legal
|
£4,000
|
|
Accountancy and Audit (additional to Forum)
|
£2,000
|
|
Marketing and Advertising
|
£2,000
|
|
Repairs and Maintenance
|
£2,000
|
|
Telecoms (including free wi-fi broadband)
|
£2,500
|
|
Sundries
|
£1,500
|
|
Rates (as charitable limited to café and possible ‘commercial’ unit)
|
£4,000
|
|
Total costs
|
£58,500
|
|
Income
The income generation of the building is driven primarily by the leasing of space, as shown below. This covers a spectrum from the hire of a room for an hour to the long term lease of space to, for example, the café operator.
|
INCOME (annual)
|
|
|
Café (franchised – private operator)
|
£12,000
|
|
Crèche (franchised to community business)
|
£10,000
|
|
Commercial Suite (let to social economy organisation, e.g., community gym)
|
£8,000
|
|
Meetings: conference suite at 200 hours at commercial rate £60/hr, 800 hours at cultural and community rate at £18 (30% of commercial), 500 hours uncharged community use (charges net of refreshments costs)
|
£35,200
|
|
Training Suite (1000 hours a year at £15, 300 hours uncharged for local resident access training)
|
£15,000
|
|
Incubation suites (£10 psf all inclusive, 10% voids)
|
£10,000
|
|
Forum Office space
|
-
|
|
Total
|
£90,200
|
|
Sustainability : Net Annual Operating Surplus and Viability
|
Net Annual Operating Surplus (Surplus of Income over costs)
|
£90,200
|
|
- £58,500
|
|
£31,700
|
|
|
|
|
The above table shows that the building generates a surplus over its operating costs that would be sufficient to ensure its survival and development.
In relation to the robustness of this viability, analysis of the income stream shows that the building remains viable if any single income stream fails (note that there is a caretaking saving where meetings use falls short of target).
Additional Building ‘Gift’
The value of the ‘building gift’, the uncharged provision to the Donegall Pass community, is around £10,000 a year in relation to the Forum’s offices, and a further £15,000 in uncharged meetings use and training, a total of £25,000 pa.
9. CONCLUSION
This concept study has reached a number of robust conclusions:
- The subject building, the former Inclusion Zone, that lies derelict in a prominent site in the middle of Donegall Pass can be a focus for significant regeneration
- There is no shortage of potential uses for the site, the Pass area needing a arrange of community focused provision, from health to youth to training to jobs to community empowerment, as well as tapping into the potential offered by the proximity to the café culture of the Botanic area and the business needs of the city centre, for example for meeting rooms
- The sheer diversity and scale of potential occupiers requires choices to be made and the study suggests that two key areas – health and youth – are so substantial a requirement that they argue for their own dedicated provision. The Inclusion Zone analysis should therefore be seen as kicking off a much larger study as to provision along the entire Pass
- A focus as a community hub would enable the Donegall Pass Community Forum to move from their current offices into a space where they could provide more and engage better with the local community. This sense of engagement is key to how the building could act, in that a café frontage will attract casual visitors, while provision such training rooms can then deepen that contact
- This calls for a series of uses in the building, which, importantly, gives it a broad base of income streams, which in turn can provide sustainability
- These uses will change over time, so a key requirement is for flexibility in the accommodation offered
- Flexibility permits different client groups comprising all ages, genders and backgrounds, to be serviced through the day and week, with perhaps a space holding a music event for pre-school children in the morning, a training event for unemployed in the afternoon and rented out for business use in the evening, or perhaps a cultural event. In this way the building is open for all and a true ‘inclusion zone’.
- This need for flexibility, coupled with the need for accessibility, argues for a new building, one that makes best use of the site, and which is of the scale necessary to create sustainability and achieve maximum impact, where uses work together
- The delivery of the project will require around £2.5m in capital support, to cover construction costs, fees and fit-out. The project can, though, be capable of meeting its operating costs thereafter.
|